Concrete and masonry
Concrete slab and gravel base calculator
Most slabs sit on a compacted gravel base. Enter both thicknesses once and get the concrete and the gravel you need, with the working shown.
Last reviewed: November 25, 2026
How the two volumes are calculated
Each layer is length × width × depth, with depth converted from inches to feet and the total divided by 27 for cubic yards. The concrete uses the slab size. The gravel uses the base size, which grows if the base extends past the slab edges. Gravel yards are then multiplied by tons per yard.
Worked example. A 12 ft × 10 ft slab, 4 in thick, on a 4 in base with no overhang. Each layer is 40 ft³. With 10% waste, that is 1.63 yd³ of concrete (74 bags of 80 lb) and 1.63 yd³ of gravel, about 2.2 tons at 1.35 t/yd³.
Why the base matters to your order
The gravel base is bought separately from the concrete, often from a different supplier and by a different unit. Loose gravel also settles when compacted, and highway specifications use heavier compacted weights per yard than the loose planning figures (see the gravel calculator for the sources). Ask your supplier for their weight per yard and how much extra they advise.
Bag yields and the effect of an uneven base on concrete are covered on the concrete slab calculator page, with sources. To count rebar for the same slab, use the rebar calculator.
Checklist before you order
- Confirm the thicknesses. Take the slab thickness from your plans and the base depth from your supplier or local requirements. This tool does not recommend either.
- Choose a waste allowance. Uneven ground and a settling base use more material than a flat estimate. The 10% default is our own planning value.
- Ask each supplier for their weight per yard. Gravel is sold by the ton or the yard, and compacted weights are heavier than loose ones.
- Check minimum loads and delivery fees. Gravel and ready-mix usually come from different suppliers with their own minimums.
- Add rebar if your plan calls for it. Use the rebar calculator with the same slab size.
The layers of a slab, from the ground up
| Layer | What it is | In this tool |
|---|---|---|
| Subgrade | The natural or prepared soil under everything | Not counted |
| Subbase (gravel base) | A compacted granular layer that gives uniform support | Gravel depth and tons |
| Vapor retarder | An optional sheet that slows moisture from below | Not counted |
| Concrete slab | The poured layer | Cubic yards and bags |
Do you need gravel under a slab?
University of Wisconsin Extension guidance for concrete slabs on the ground says a subbase may not be necessary if the subgrade gives adequate support. Where grading and compaction do not produce a uniform subgrade, it says a granular subbase must be used, with a minimum thickness of 4 in of compacted material (UW Extension). That guidance was written for agricultural buildings, so confirm what your project, soil and local code require.
Placing the base in lifts
The same guidance says a thicker subbase goes in layers of 4 to 6 in, each compacted, and that adding thickness beyond 4 in gives only minor gains in support. It also says concrete should not be placed directly on a vapor retarder: where one is used, a 6 to 8 in layer of compacted, self-draining granular fill goes over it (UW Extension). If your plan includes that layer, add it to the base depth in the calculator.
Frequently asked questions
How much gravel do I need under a 12×10 slab?
For a 12 ft × 10 ft area with a 4 in base and no overhang, the base is 40 ft³, or 1.48 yd³. With 10% waste it is 1.63 yd³, about 2.2 tons at 1.35 tons per yard. Your base depth and gravel type change this.
How deep should the gravel base be?
It depends on the soil, the load and local requirements, so this tool does not recommend a depth. Ask your supplier or local building authority, and enter their figure above.
Should the base be wider than the slab?
Some jobs extend the base past the slab edges. If yours does, enter the extra distance on each side and the gravel result increases to match.
Do I need gravel under a concrete slab?
Not always. University of Wisconsin Extension guidance says a subbase may be unnecessary when the subgrade supports the slab, but a granular subbase is needed when the subgrade is uneven. Check your soil and local code.
Can I put all the gravel in at once?
A thick base should go in layers. UW Extension guidance gives 4 to 6 in lifts, each compacted. Plan for the layers when you order, and confirm the weight per yard with your supplier.
Sources
- University of Wisconsin Extension: Concrete slabs on the ground (ch. 6)
- University of Wisconsin Extension: Soils, subgrade and subbase (ch. 4)
- Quikrete: Concrete Mix 1101 data sheet (bag yield)
- Designing Buildings: Converting between weight and volume (stone density)
This calculator gives estimates for planning and ordering. It does not replace a supplier’s quote, local building codes or professional design.